Below is a compact, practical guide you can use on a blog or for quick design checks. I cite the code and explanatory notes so you can check the clauses.


Check Below for Free Pdf Download of Wind Load Calculation & Nominal Payable Calculation Excel Spread Sheet

Wind load Calculation

Design wind speed at height z is calculated as
Vz = Vb ร— k1 ร— k2 ร— k3 ร— k4,
where

  • Vb = basic wind speed from the IS-map (50-yr return).
  • k1 = probability (risk) factor (depends on life/importance).
  • k2 = terrain, height & structure-size factor (from Table 2).
  • k3 = topography factor (hills, escarpments โ€” usually 1.0 for flat).
  • k4 = cyclonic importance factor (applies in cyclonic areas per clause).

Design wind pressure at height z:
pz = 0.6 ร— Vzยฒ (units: N/mยฒ).

Wind force on an element (wall/roof panel):
F = pz ร— A ร— (Cpe โˆ’ Cpi) ร— Kd,
where Cpe = external pressure coefficient, Cpi = internal pressure coefficient, A = projected area, and Kd = wind directionality factor (typical Kd = 0.9 for frames; for local cladding pressures sometimes Kd = 1.0).

Wind Data:
Basic Wind Speed Vb = 50.00 m/s
(As per DBR)
Risk coefficient K1 = 1.00
(for General Buildings as per DBR)
Terrain, height and structure size factor K2 = 1.05
(from Table2 of IS:875 III, for Terrain category 2 & Class B)
Topography factor K3 = 1.00
( As per DBR)
Importance Factor for cyclonic region K4 = 1.15

Design Wind Speed Vz = Vbk1k2k3k4 = 60.38 m/s
Design Wind Pressure Pz = 0.6 Vz2 = 2187.1 N/m2
Pz = 2.19 kN/m2
Wind directional factor, kd = 1.00
Combination factor, Kc = 1.00
For open framed structure kc = 1
For closed framed structure kc = 0.9
Area averaging Factor, Ka = 0.80

Pd = kdkakc*Pz Pd = 1.7497

Load on open structure

Wind force on member, F=CfxAexPd

Cf  –  Net force coefficient0.8Table 24 IS875-part3
LevelHeight above ground                      “m”Pd   (kN/mยฒ)Cf * Pd   (kN/mยฒ)
Level-10.00  –5.001.5871.27
Level-25.00  –10.001.5871.27
Level-310.0015.001.7501.40
Transverse Wind Force due to Pipe:
Tributary Area: Ae = (D + W tan10) x Bent Spacing(m)
where, D is maximum pipe diameter at respective level & W is Width of Pipe Rack
z, (m)Dia. of Pipe – D (m)Usuable Width of PR,(m)LengthAf, (m2)F=CfxAexPd, (kNRemarks
5.000.7626.06.0011.0514.03230″ dia pipe
7.500.7626.06.0011.0514.032
12.500.7626.06.0011.0515.473
Transverse Wind Force due to Cable Tray:
Tributary Area: Ae = (D + W tan10) x Bent Spacing(m)
No. of Trays = 3 no’s
z, (m)cable tray height (m)Usuable Width of PR,(m)LengthAf, (m2)F=CfxAexPd, (kNMoment kNm (0.9m ht)
10.000.1506.06.0022.1428.1125.30

2 responses to “Wind Load Calculation IS 875 Part 3 2015”

  1. Pia Manni Avatar

    I like your blog.

  2. fintechbase Avatar

    Nice post. I was checking continuously this blog and I am impressed!

    Extremely useful information specifically the last
    part ๐Ÿ™‚ I care for such info a lot. I was looking
    for this particular info for a long time. Thank you and best of luck.

Almost there!
We are confirming your order with